Battery Energy Storage Systems (BESS): The Complete Electrical Design Guide for Ontario

Diagram: six battery racks on a DC bus through a DC disconnect and the power conversion system to the switchgear and utility connection

Battery energy storage is no longer experimental - it's a fast-growing part of Ontario's electrical infrastructure. From peak shaving in commercial buildings to grid-scale renewable integration, BESS projects are accelerating. But the electrical design requirements are complex, spanning CEC rules, UL certifications, fire codes, and utility interconnection agreements. This guide covers everything an engineer or building owner needs to know.

Why BESS is Exploding in Ontario

Three forces are driving BESS adoption across Ontario:

  • Global Adjustment charges: Ontario's Class A customers pay Global Adjustment based on their share of the top five peak hours - BESS peak shaving in those hours can cut this charge
  • Solar + Storage economics: With net metering evolving, behind-the-meter storage maximizes self-consumption of on-site solar generation
  • EV charging demand: Level 3 DC fast chargers create massive demand spikes - BESS buffers these peaks without costly utility upgrades

Applicable Codes and Standards

BESS design in Ontario requires compliance with a matrix of overlapping codes. Missing even one can halt your project:

Standard Scope Why It Matters
OESC (CSA C22.1:24 + Ontario amendments)All electrical wiring and connectionsFoundational - every conductor, disconnect, and overcurrent device must comply
ANSI/CAN/UL 9540 (BMS: CSA C22.2 No. 340)Complete BESS system safetySystem-level certification - batteries + inverters + controls tested together
UL 1973Battery cell and module safetyEnsures individual battery units meet thermal, mechanical, and electrical safety
UL 9540AThermal runaway fire propagationCommonly requested by fire and building officials to assess worst-case fire scenarios
NFPA 855Installation of stationary energy storageSiting, separation distances, ventilation, fire suppression requirements
CSA C22.2 No. 107.1 / UL 1741Inverter safety and grid interconnectionAnti-islanding protection - prevents backfeeding the grid during outages
Ontario Building Code (OBC)Building integrationStructural loads, fire ratings, egress paths near BESS installations
ESA Bulletin 64-7-3Ontario-specific requirementsESS approval: certified to ANSI/CAN/UL 9540 or field-evaluated (OESC Rule 2-024)

BESS Sizing: The Engineering Process

Proper BESS sizing starts with understanding your load profile. The key parameters:

Parameter Unit How to Determine
Peak demandkW12-month utility billing data - highest 15-min demand reading
Target demand reductionkWFinancial analysis - how much peak shaving pays back within ROI target
Discharge durationhoursLoad profile analysis - how long does the peak typically last?
Energy capacitykWhkW × hours ÷ depth of discharge factor (typically 80-90% for lithium-ion)
Round-trip efficiency%Typically 85-92% for lithium-ion - energy lost in charge/discharge cycle
Example: A commercial building with a 500 kW target demand reduction (not its peak demand) and 2-hour peaks needs a minimum 500 kW / 1,000 kWh system. Accounting for 85% depth of discharge and about 95% discharge-path efficiency (battery and inverter, roughly half the losses of a 90% round trip): 1,000 ÷ 0.85 ÷ 0.95 ≈ 1,238 kWh at beginning of life. Then add an end-of-life degradation allowance: divide by the end-of-life capacity fraction the manufacturer warrants to set the nameplate capacity.

Electrical System Architecture

A BESS connects to the building's electrical system through several critical components:

  • Battery modules: Lithium-ion (LFP or NMC chemistry) rack-mounted in climate-controlled enclosures
  • Battery Management System (BMS): Monitors cell voltage, temperature, and state of charge - triggers shutdown on anomaly
  • Bidirectional inverter: Converts DC battery power to AC (and vice versa) - must be certified to CSA C22.2 No. 107.1 (UL 1741 in the US)
  • AC disconnect: Visible, lockable disconnect per CEC - required at the point of common coupling (PCC)
  • DC disconnect and fusing: String-level protection per CEC Section 64 - sized for maximum fault current
  • Revenue-grade metering: Required by utility for net metering or demand response program participation

Utility Interconnection: Hydro One & Toronto Hydro

Connecting a BESS to the grid in Ontario requires formal utility approval. The process mirrors new service connections but adds energy export considerations:

  • Connection Impact Assessment (CIA): Generally required above the micro-embedded limit (>12 kW since May 1, 2026) - utility evaluates grid capacity to accept your system
  • Anti-islanding protection: OESC Section 84 and the utility's technical requirements (e.g. CSA C22.3 No. 9) - prevents energizing the grid during utility outages
  • Protection relay coordination: Must coordinate with utility's relay settings to prevent nuisance tripping
  • ESA permit: Ontario electrical permit required - ESA inspects the complete installation

Fire Safety: The Critical Design Constraint

Lithium-ion battery fires are rare but catastrophic. Fire and building officials are increasingly scrutinizing BESS installations. Key requirements per NFPA 855 (a reference standard, not adopted by Ontario regulation):

Requirement Indoor Installation Outdoor Installation
Fire-rated room2-hour fire rating minimumN/A (separation distance instead)
Separation distanceN/A3 m from buildings; unit spacing per NFPA 855 or test data
VentilationMechanical - sized for thermal runaway gas volumeNatural ventilation typically sufficient
Fire suppressionAutomatic sprinklers (NFPA 13); alternatives only where testing supports themFire department access required
Gas detectionWhere part of the NFPA 69 explosion-prevention design (confirm with the product's UL 9540A data) - H2, CO, and VOC sensorsInside containerized systems, where part of the NFPA 69 explosion-prevention design (confirm with the product's UL 9540A data)
Explosion controlDeflagration venting or suppressionContainer venting per UL 9540A test results
SignageCE Code Rule 2-306 (CSA Z462) + NFPA 855 labels on all access pointsSame - plus reflective markers for night access
UL 9540A test data is a key document fire and building officials may request. It proves your specific battery chemistry has been tested for thermal runaway propagation at the cell, module, and unit level. Have the UL 9540A report ready before permit review.

Common Design Mistakes

  • Undersizing conductors: BESS operates at high DC currents - voltage drop on DC strings directly reduces efficiency and can cause overheating
  • Ignoring harmonics: Bidirectional inverters inject harmonics - harmonic limits (often IEEE 519) may be required by the utility at the PCC
  • Missing arc flash analysis: BESS DC systems can sustain arcs - arc flash studies must include the battery system
  • No grounding study: DC grounding in BESS systems requires careful analysis - improper grounding can create stray current and corrosion issues
  • Skipping the load study: Without a proper load calculation, BESS systems are either oversized (wasted capital) or undersized (insufficient peak shaving)

Frequently Asked Questions

What codes govern BESS in Ontario?

ANSI/CAN/UL 9540, OESC Section 64, NFPA 855 (reference only in Ontario) and CSA C22.2 No. 340 (BMS). See our solar PV guide for related standards.

How do you size a BESS?

Load profile analysis, use case definition, discharge duration, and degradation factor. See our load calculation guide.

What fire safety is needed for BESS?

NFPA 855 for spacing/ventilation, UL 9540A thermal runaway testing, and 2-hour fire separation for indoor installations.

Related service

Electrical engineering

ETEM can review existing electrical capacity, distribution constraints and proposed loads to define the required design and upgrade scope.

Electrical engineering