Service Entrance Design: Utility Coordination That Makes or Breaks Your Project Timeline

The utility doesn't care about your construction schedule. A service entrance application takes 4–12 weeks — and if your load letter is wrong or your CT cabinet doesn't match the LDC's approved list, you restart the clock.

Commercial Service Entrance

Service Types in Ontario

Service TypeVoltageTypical ApplicationMetering
120/240V 1Φ240V single-phaseResidential, small retailSelf-contained meter (200A max)
120/208V 3Φ208V three-phase wyeSmall commercial, officesSelf-contained or CT metering
347/600V 3Φ600V three-phase wyeIndustrial, large commercialCT metering required
4.16kV / 13.8kVMedium voltageLarge industrial, campusVT/CT metering, customer substation

The Load Letter

Every service application starts with a P.Eng-sealed load letter specifying connected load, demand load (CEC Section 8), service size in amps, voltage, and 20–25% future allowance.

CT Cabinet & Metering

Service SizeMetering TypeCT Ratio
≤ 200ASelf-contained meter baseN/A
201–400ACT metering400:5
401–800ACT metering800:5
801–1200ACT metering1200:5
1201–2000ACT metering2000:5
Critical: CT cabinets must be from the LDC's approved equipment list. Hydro One, Toronto Hydro, and Alectra each have different approved models. Wrong CT cabinet = rip out and replace at your cost.

Service Conductor Sizing (CEC Rule 4-006)

Service SizeMin Conductor (Cu, 90°C)Conduit
200A3/0 AWG2"
400A500 kcmil3"
600A2 × 3/0 AWG per phase2 × 2"
800A2 × 350 kcmil per phase2 × 3"
1200A3 × 350 kcmil per phase3 × 3"
2000ABus ductBus duct

Grounding Electrode System (CEC Rule 10-700)

  • GEC — sized per CEC Table 17
  • Ground rod — 3m driven copper-clad, 16mm diameter
  • Water pipe bond — within 1.5m of building entry
  • Ufer ground — 6m of #4 AWG bare copper in footing

Utility Coordination Timeline

PhaseDurationAction
Load letter submissionWeek 0P.Eng sealed load letter + site plan
Offer to connectWeeks 4–8LDC reviews and issues conditions
Accept + pay contributionWeek 8–10Capital contribution if required
LDC installs transformerWeeks 10–16Pad-mount or pole-mount transformer
Service connectionWeek 16+After ESA inspection, LDC energizes
Pro tip: Submit the load letter as early as possible — even before detailed design. Use conservative estimates. Easier to reduce later than increase after transformer is sized.
Disclaimer: This article provides general engineering guidance. Verify against current CEC, OESC, and your LDC's conditions of service. Consult a P.Eng for project-specific applications.

Need Service Entrance Engineering?

ETEM Engineering handles complete service entrance design — load calculations, P.Eng load letters, single-line diagrams, CT cabinet specs, and coordination with Hydro One, Toronto Hydro, and Alectra.

Get a Free Consultation