The 5% Rule: Why Your Long Cable Runs Are Failing CEC Inspection
That 150-metre cable run to the parking garage looked fine on paper. The wire was sized for ampacity. The breaker was correct. But the ESA inspector failed it anyway — because of voltage drop. Here's the rule every engineer needs to master.
What CEC Rule 8-102 Actually Says
The Canadian Electrical Code, Rule 8-102, states that the voltage drop from the supply side of the service to the point of utilization shall not exceed 5% of the nominal circuit voltage. This is not a suggestion — it's a hard limit that ESA inspectors enforce.
CEC Rule 8-102: The voltage drop in an installation from the supply side of the consumer's service to the point of utilization shall not exceed 5%.
For a 120V circuit, that's a maximum of 6V. For a 208V circuit, it's 10.4V. For a 347V lighting circuit, it's 17.35V.
The code further recommends that feeder voltage drop not exceed 3%, leaving the remaining 2% for branch circuits. This 3%+2% split is best practice, though the inspector technically only enforces the total 5%.
The Voltage Drop Formulas
For copper conductors in steel conduit (most common commercial installation):
Single Phase:
VD = 2 × I × L × R / 1000
Three Phase:
VD = √3 × I × L × R / 1000
Where: I = current (A), L = one-way length (m), R = conductor resistance (Ω/km)
Conductor Resistance Table (Copper, 75°C)
| Wire Size (AWG/kcmil) | AC Resistance in Steel Conduit (Ω/km) | AC Resistance in Non-metallic (Ω/km) | Typical Ampacity (75°C) |
|---|---|---|---|
| #14 | 10.2 | 10.2 | 15A |
| #12 | 6.50 | 6.50 | 20A |
| #10 | 4.07 | 4.07 | 30A |
| #8 | 2.56 | 2.56 | 45A |
| #6 | 1.61 | 1.61 | 65A |
| #4 | 1.02 | 1.02 | 85A |
| #3 | 0.810 | 0.810 | 100A |
| #2 | 0.656 | 0.643 | 115A |
| #1 | 0.524 | 0.510 | 130A |
| 1/0 | 0.420 | 0.404 | 150A |
| 2/0 | 0.335 | 0.321 | 175A |
| 3/0 | 0.269 | 0.254 | 200A |
| 4/0 | 0.217 | 0.203 | 230A |
| 250 kcmil | 0.187 | 0.171 | 255A |
| 350 kcmil | 0.138 | 0.125 | 310A |
| 500 kcmil | 0.105 | 0.0902 | 380A |
Worked Example: Parking Garage EV Panel
You're feeding a 100A, 208V, 3-phase EV charging panel located 150 metres from the electrical room. The engineer specifies #1 AWG copper in steel conduit.
Step 1: Calculate Voltage Drop
VD = √3 × 100A × 150m × 0.524 Ω/km / 1000
VD = 1.732 × 100 × 150 × 0.000524
VD = 13.6V
Step 2: Check Against 5% Limit
Maximum allowed VD = 208V × 5% = 10.4V
Calculated VD = 13.6V → FAILS (6.5%)
Step 3: Upsize the Conductor
Try 3/0 AWG copper:
VD = 1.732 × 100 × 150 × 0.000269 = 6.99V (3.4%) → PASSES ✓
Notice the gap: #1 AWG has plenty of ampacity for 100A (rated 130A), but fails on voltage drop. This is the classic trap — the wire is big enough to carry the current safely, but the voltage arriving at the load is too low for equipment to operate properly.
When Voltage Drop Matters Most
- Underground parking garages: Long horizontal runs from the electrical room to the far end of the garage
- Site lighting circuits: Parking lot poles 200+ metres from the panel on 347V circuits
- Motor loads: Pumps, fans, and compressors in mechanical penthouses or remote buildings
- Construction power: Temporary panels fed by long cable runs across job sites
Common Mistakes
- Sizing wire for ampacity only — the wire may carry the current safely but deliver insufficient voltage
- Using DC resistance instead of AC resistance — AC resistance in steel conduit is higher due to skin effect and conduit losses
- Measuring one-way instead of round-trip for single-phase — the "2×" factor in the formula accounts for the return path
- Not accounting for temperature derating — resistance increases with temperature; a hot conduit run has higher voltage drop
Download the Voltage Drop Calculator
Get our Excel-based voltage drop calculator — pre-loaded with CEC conductor resistance tables and automatic pass/fail checking.
Need a Voltage Drop Analysis?
ETEM Engineering performs detailed voltage drop studies for long feeders, parking structures, and site distribution systems. We ensure your designs pass ESA inspection on the first submission.
Get a Free Consultation