Solar PV System Design & Net Metering: The Ontario Engineer's Guide

Ontario's net metering program lets building owners offset their hydro bill with rooftop solar — but the electrical design has to satisfy CEC Section 64, ESA inspection, and utility interconnection requirements simultaneously. Here's the engineering behind a code-compliant PV installation.

Commercial Rooftop Solar PV Installation

System Architecture: Grid-Tied PV

The vast majority of Ontario commercial PV installations are grid-tied without battery storage. The system components:

Component Function Key Specification
PV ModulesConvert sunlight to DC electricityTypically 400–550W monocrystalline, Voc 40–50V per module
String InverterConvert DC to AC (grid-synchronous)Must be CSA/UL listed, anti-islanding per IEEE 1547
AC DisconnectVisible, lockable disconnect for utility accessRequired by utility — must be within sight of meter
DC DisconnectIsolate PV array from inverterCEC Rule 64-112 — required for maintenance
Revenue MeterBidirectional meter tracking import/exportProvided by LDC (Local Distribution Company)
Rapid ShutdownDe-energize rooftop conductors for firefighter safetyCEC Rule 64-218 — within 30 seconds, to ≤30V within array

CEC Section 64 — Solar Photovoltaic Systems

Section 64 is the dedicated CEC section for PV installations. Key rules:

CEC Rule Requirement
64-060PV source circuit conductors shall be sized at 125% of Isc (short circuit current) of the module string
64-062Overcurrent protection for PV source circuits — maximum fuse rating per module manufacturer datasheet
64-076PV system output connected to the supply side of the service disconnect requires utility approval
64-112DC disconnect means required — must be accessible and lockable
64-210The 120% rule — PV backfeed breaker + main breaker ≤ 120% of busbar rating
64-218Rapid shutdown — array conductors must be reduced to ≤30V within 30 seconds of initiation

The 120% Rule (CEC Rule 64-210)

The sum of the PV backfeed breaker rating and the main breaker rating shall not exceed 120% of the busbar rating.

Example: 200A busbar panel → 200A × 1.2 = 240A maximum → 240A − 200A main = 40A maximum PV backfeed breaker
At 240V single-phase: 40A × 240V = 9.6 kW maximum inverter output

If the PV system exceeds this limit, options include:

  • Upgrade the busbar — install a higher-rated panel
  • Supply-side connection — connect PV between meter and main breaker (requires utility approval per Rule 64-076)
  • Line-side tap — connect directly to service entrance conductors (complex, P.Eng design required)

Net Metering in Ontario

Parameter Detail
ProgramOntario Net Metering (O. Reg. 541/05)
Maximum size500 kW (must be sized to offset own consumption)
Meter typeBidirectional — credits excess generation at same rate as consumption
Credit rolloverExcess credits roll forward for 12 months, then reset to zero
Eligible LDCsHydro One, Toronto Hydro, Alectra, and all Ontario LDCs
ApplicationSubmit to your LDC with single-line diagram, P.Eng stamp, ESA notification

Utility Interconnection Process

  • Step 1: Pre-application — confirm service capacity and transformer sizing with LDC
  • Step 2: Engineering design — single-line diagram with P.Eng seal
  • Step 3: ESA permit — file notification with Electrical Safety Authority
  • Step 4: Installation and ESA inspection
  • Step 5: LDC meter exchange — install bidirectional meter
  • Step 6: Authorization to connect (ATC) — LDC approves grid connection

Inverter Sizing

Parameter Rule
DC/AC ratioTypically 1.1–1.3 (e.g., 13 kW DC array → 10 kW inverter)
Input voltage windowString Voc (at lowest temp) must be within inverter max Vdc rating
MPPT rangeString Vmp must fall within inverter MPPT voltage window at all operating temperatures
Anti-islandingInverter must cease export within 2 seconds of grid loss (IEEE 1547 / CSA C22.2 No. 107.1)
Disclaimer: This article provides general engineering guidance for educational purposes. Always verify requirements against the current edition of the Canadian Electrical Code (CEC), Ontario Electrical Safety Code (OESC), and your Local Distribution Company's interconnection standards. Consult a licensed Professional Engineer (P.Eng) for project-specific applications.

Need Solar PV Engineering Design?

ETEM Engineering provides complete PV system design — from string sizing and inverter selection to single-line diagrams, P.Eng sealed drawings, and utility interconnection coordination.

Get a Free Consultation